Operon Daily · What moved

NRC completes 80-MWe Xe-100 safety review

As produced 12 source documents linked

Good morning. X-energy’s Xe-100 cleared a major NRC safety review, while Urenco USA produced its first commercial cylinder of LEU+. The day also brings a practical test of whether advanced nuclear developers can turn technical progress into US manufacturing and deployment.

Top Signals

1. NRC completes 80-MWe Xe-100 safety review

The US Nuclear Regulatory Commission completed its safety review for X-energy’s Xe-100 high-temperature gas-cooled reactor, issuing the Final Safety Evaluation Report needed for a construction permit under 10 CFR Part 50. The initial deployment is planned for Dow’s UCC Seadrift Operations facility in Long Mott, Texas, and each reactor produces 80 MWe or 200 MW of high-temperature process heat. The review establishes a “replicable pathway” for future Xe-100 licensing, although later applications will still receive individual evaluations. As the article puts it, “The Xe-100 design leverages passive physics safety and Tri-structural Isotropic (TRISO) particle fuel.”

What this review means:

  • Industrial deployment: The Seadrift project is slated to become the first grid-scale advanced reactor operating at a US industrial site.
  • Site flexibility: Xe-100’s passive safety design and TRISO fuel support a 400-metre emergency planning zone, compared with the 10-mile radius associated with traditional light-water reactors.
  • Commercial context: The project was developed under the Department of Energy’s Advanced Reactor Demonstration Program, with Amazon holding roughly a 23% stake in X-energy.
  • Next milestone: X-energy and Dow now move toward the construction-permit decision enabled by the completed Part 50 safety review.

Why it matters: This gives X-energy and Dow a concrete licensing precedent for an industrial-site advanced reactor and gives other developers a benchmark for narrowing the regulatory work between a completed design review and a construction permit.

2. Saltfoss targets US licensing for floating reactor in 2027

Danish developer Saltfoss, formerly known as Seaborg, plans to expand its US operations and submit a Regulatory Engagement Plan to the Nuclear Regulatory Commission in the first quarter of 2027. The company is targeting the NRC’s Part 53 framework for its seaMSR floating power plant and says it could become the first advanced reactor developer licensed under the new framework, as well as the first advanced maritime small modular reactor licensed anywhere. World Nuclear News reports that Saltfoss describes Part 53 as a framework that “establishes a risk-informed, performance-based, and technology-inclusive regulatory framework as an alternative for the licensing and regulation of commercial nuclear plants.”

What Saltfoss is proposing:

  • US integration: Saltfoss plans to increase US activity in reactor assembly, fuel loading and final power-plant integration.
  • Korean manufacturing: Its partner Samsung Heavy Industries will continue manufacturing the power barges in South Korea.
  • Safety case: The company says its fuel salt solidifies below about 500 degrees Celsius, allowing the reactor to shut down and drain by gravity without operator action or external power.
  • Market targets: Saltfoss identifies coastal industrial power and heat, grid baseload and hyperscale data centers as potential uses.

Why it matters: Saltfoss and the NRC will put Part 53’s technology-inclusive approach to a visible test when the company submits its engagement plan in the first quarter of 2027, while the US-Korean manufacturing split offers a model for building maritime reactors across allied supply chains.

By Issue

Nuclear waste / spent fuel

Deep Isolation begins Texas well-pad construction

Deep Isolation Nuclear has started site preparation and well-pad construction at its Deep Borehole Demonstration Center near Cameron, Texas. The work moves the company’s Commercialisation Pilot from engineering design into field execution for a full-scale, at-depth nuclear waste disposal demonstration.

The project will test Deep Isolation’s patented Universal Canister System using non-radioactive simulant packages, including handling, emplacement and retrieval. The company is working with Halliburton, Amentum, NAC International and Occlusion Nuclear Solutions. Surface infrastructure is forecast to finish in December 2026, after which drilling, casing and cementing will begin.

Other developments

Urenco USA starts first commercial LEU+ production

Urenco USA has produced its first commercial cylinder of low-enriched uranium plus, or LEU+, at its National Enrichment Facility in New Mexico. The company’s NRC authorization, issued in September 2025, permits enrichment up to 10% U-235, and all of the plant’s gas centrifuge cascades are licensed to produce LEU+. Director Jody Blackshear, Managing Director of Urenco USA, said, “A tremendous amount of work has gone into preparing our plant and our staff to reach this achievement.”

The World Nuclear News report and Urenco USA’s announcement identify the cylinder as the first commercial LEU+ production in the Western world. The product can serve existing light-water reactors and advanced reactor designs that use higher enrichment, while Urenco USA plans to expand its New Mexico capacity to more than 7 million separative work units over the next decade.

Data-center nuclear

PSEG Power plans 200-MW Salem uprate

PSEG Power and Constellation Energy plan a 200-MW uprate at the jointly owned Salem nuclear plant in New Jersey. PSEG Power would receive 112 MW of the additional capacity, with Constellation owning the remainder, supporting a nuclear-focused power purchase agreement with Google. The SEC filing also reports that Salem 1 faces an extended refueling outage while the companies conduct further testing and inspect degraded equipment.

PSEG continues developing contracts with large-load customers involving existing nuclear generation and future upgrades, according to Utility Dive’s account. Gov. Mikie Sherrill’s administration and New Jersey utility regulators are also working with Public Service Electric and Gas to limit electric cost increases and consider new regulatory models. The proposed uprate puts existing nuclear capacity at the center of data-center supply planning, but its timing remains tied to the Salem 1 inspection and repair process.

Grants and Funding

DOE selects $8.5 million for 28 INFUSE projects

The Department of Energy’s Office of Science awarded $8.5 million across 28 projects through the Innovation Network for Fusion Energy, or INFUSE. The INFUSE award list, FY2027 application page, 2026 project abstracts and award coverage show the program’s practical structure:

  • Recipients: 22 companies will work with 10 national laboratories and nine universities.
  • New entrants: Nine companies will receive INFUSE awards for the first time.
  • Technical scope: Projects cover high-temperature superconducting magnets, reactor materials, diagnostics, fuel-cycle work and engineering challenges.
  • Company projects: Helion Energy will study plasma instabilities at Princeton Plasma Physics Laboratory’s FLARE facility; Realta Fusion will pursue magnetic-mirror simulation tools and a low-tritium-inventory fuel-cycle design; Terra Fusion will refine its centrifugal-mirror prototype; and Westinghouse Electric Company will test neutron-conversion materials for fusion breeder-blanket measurements.

The program gives fusion companies access to national-laboratory and university capabilities at the stage where materials, diagnostics and fuel-cycle choices can determine whether a design moves toward commercial demonstration.

That’s where things stand today. More tomorrow morning.

About this issue. The general edition of the Operon Daily for Wednesday, November 4, 2026, published as it was produced. Every claim links to the document it came from; items judged routine or already covered were held back. Client briefings are written around each client's own list and are never published.

Want this built around your own dockets and peers? Start a 60-day pilot.

All issues · RSS